*Assist
in the development of the overall concept of the project.
-
*Assist
in providing liaison and coordination among government authorities,
utility companies, and other groups, evolving a basic program for
the project.
-
*To
fully acquaint the Owner and other members of the Management Team
of the labour agreements applicable for the duration of the project.
-
4. Prepare a preliminary budget as soon as the concept of the overall
project is developed and break down where necessary for each phase
of the work.
-
*Prepare
a preliminary master schedule following detailed studies with all
parties concerned, incorporating the sequence and timing of the required
basic program decisions, design time, documentation, tender calls,
bid evaluations and contract awards as well as on-site construction
activities.
-
*As
design proceeds, evaluate possible alternatives in order to permit
the selection of the most suitable and economical materials and methods
that will satisfy the architectural concept.
-
*Revise
and update the preliminary budget on a continuing basis to reflect
the valuation of the program and the timing of its various phases.
-
*Revise
and update the preliminary schedule as the design proceeds.
-
*Establish
the final overall budget for the project, based on the latest working
drawings, and present for the Owner's approval.
-
*Finalize
the master schedule and establish the manpower requirements. Where
necessary, break down this schedule into individual networks or each
phase of the project showing the sequence and timing for the main
construction operations and the desired completion dates of the various
phases.
-
*Establish
a cost breakdown for control purposes and prepare a cash flow for
the project.